27th Street Project New Traffic Alignment Impact

Phase One 27th Street Impact:

Over the next few days the work zone will be dynamic in an effort to move into the new alignment that will have two lanes of traffic flowing in each direction on CO 82. Turn lanes from CO 82 to 27th street will be reopened. The new alignment allows the team to begin the underpass construction under CO 82 near the RFTA BRT station. 27th Street will be open with some lane impacts. Motorists are encouraged to use alternate routes around this area to balance the traffic volumes during the peak morning and evening commutes. Delays should be expected.


Pedestrians must use the identified alternate pedestrian routes and do not cross at CO 82 & 27th Street.


The project team will be working on Saturday, July 29 to place barriers and complete striping on the new alignment. Commuters should be prepared for the new alignment to be operational on Monday, July 31st.


Phase 1 new traffic alignment

  1. Move CO 82 traffic to temporary realignment shown on Friday, July 28.

  2. Construct east half of CO 82 underpass and related improvements on southeast corner through October 2023.

  3. Thursday July 27- Friday July 28: Traffic signal and detour work continues from 6 a.m. -6 p.m., Monday-Friday.

  4. Monday, July 31- Friday, August 4: Sanitary sewer installation at the RFTA BRT station, Monday-Friday. The BRT station right way has been reduced in size.




TRAFFIC IMPACTS RFTA 27th Street Project, week of July 28-August 4